Posted on: December 23, 2022

December 23rd, 2022 - Year End Update

22-12-23 - North Site View

As the snow settles over the Pier worksite and we head in to the holidays, North Mountain Construction has cleaned up the worksite at the bottom of Hall Street and demobilized for a winter site closure.

While you may see some decking work still being completed in the next few weeks, things will remain quiet on the site until approximately April of 2023.

In the meantime, lots of planning work will be taking place in the back ground to prepare for work to continue in April with an estimated completion of the project by July 2023.

22-12-23 - North Site View

Pier photo taken December 23rd, 2022.

22-11-18 - Decking install

View of the Pier decking taken November 18th, 2022.

22-11-18 - South site view

 View to the south on November 18th, before the Ladybird Display building was erected.22-12-02 - South Site View

Ladybird display building looking south from the Pier, taken December 2, 2022

22-12-16 - Beam 3 and  11 bracing



Beam Bracing on the Pier – December 16th, 2022

22-12-22 - Parking area cleared


Parking lot at the foot of Baker Street is now available for parking till the spring of 2023.